MONTROSE AND GUNNISON COUNTIES, Colo. (KREX) — On Wednesday, the Colorado Department of Transportation and Kiewit Infrastructure Co. announced that they are altering the work hours for crews applying the final coat of paint to repaired steel on the US Highway 50 Middle Bridge and Lake Fork Bridge.
On Sunday, June 8, construction crews will work from 4 p.m. to 4 a.m. Sunday through Friday. Flaggers will direct single-lane traffic over each bridge. This is the final phase of the emergency repair project, scheduled for completion by the end of July.
The emergency repair project began in April 2024, when several steel weld cracks were detected in the US 50 Middle Bridge and similar defects were found in the US 50 Lake Fork Bridge. Both bridges had partial closures after the cracks were detec