CRANSTON – Route 2/New London Avenue in Cranston will be down to one lane in each direction as it goes under Route 37, a move that will last until mid-November 2025.

Route 2 will be down to one lane in each direction starting on Aug. 15, as crews begin work to demolish the Route 37 bridge that goes over Route 2.

The ramps and exits at the interchange on Route 37 will stay open, but the lanes will be narrowed and shift, and there will be less distance for merging, according to a news release from the Rhode Island Department of Transportation.

Rt. 37 bridge demolition will bring new closures

Sometime in November, work on the demolition of the bridge will start, bringing more closures.

The Route 37 bridge replacement is part of a larger $143 million project to repair or replace the b