HENDERSON (KTNV) — The City of Henderson has made significant progress on the Reimagine Boulder Highway project one year after breaking ground, with new traffic signals, streetlights and bus lane infrastructure now visible along the corridor.
WATCH | Jhovani Carrillo breaks down the latest developments at the project's one-year mark Henderson's Reimagine Boulder Highway project shows progress one year later
Crews have completed extensive underground and roadway work, including:
Flood protection : Installed over 20,000 feet of storm drains and five major connections near Lake Mead and Sunset to reduce flood risk.
Traffic and lighting upgrades : Upgraded wiring at all 17 intersections and installed 105 new streetlights, improving visibility and traffic flow. Laid over 50,000 feet o