Hundreds of apartments, parking spaces and retail space are in the plans.

And, as another regular season of the Yard Goats draws to a close at Dunkin’ Park , the 1960s data center just beyond center field is still standing — vacant and an eyesore — but a new view from the city’s minor league ballpark is expected at the start of next season.

“We are all working hard on a schedule that should have the center field view at Yard Goats stadium clear by opening day next year,” Jeff Auker, Hartford’s director of development services, said. “On opening day, there will be a nice clear view.”

Demolition, which could take up to six months, is expected to begin this fall, Auker said.

The state is wrapping up its review of the redevelopment plans for the site that include a $90 million applie