ROCKY RIVER, Ohio — The delayed work on I-90 eastbound between Hilliard Boulevard and Alger Road is set to begin Monday.
The Ohio Department of Transportation originally planned to reduce the lanes between Hilliard Boulevard and Alger Road last Monday, but some weather-related issues got in the way. Now, crews will make adjustments so only three of the four lanes will be open for traffic.
These restrictions will be in place until November 2026.
The work is a part of the larger Interstate 90 rehabilitation project, a $173 million project stretching from West Boulevard in Cleveland to Hilliard Boulevard in Rocky River.
Upgrades include median barrier and overhead lighting replacements, some shoulder widening and drainage improvements.
Those drainage improvements should prevent some of t