The Hafizpet railway station in Hyderabad is being redeveloped under the Amrit Bharat Scheme at a cost of Rs 29.21 crore. With 80% work completed, it will feature modern amenities like lifts, escalators, waiting halls, and divyangjan-friendly facilities by 2025
Hyderabad: The Hafizpet railway station is undergoing a major makeover as part of the redevelopment work being taken up under ‘Naya Bharat Naya Station’ initiative of Amrit Bharat Station Scheme (ABSS) of Railway Ministry.
As of date, about 80 per cent of the proposed development work has been completed. Simultaneously, all the works are in fast progress and are targeted to be completed by 2025 end. The Hafizpet railway station redevelopment is being taken up with an approximate cost of Rs 29.21 crore.
The key completed works in