Central Railway (CR) will operate two special traffic and power blocks for launching of 4 Foot Over Bridge (FOB) girders at Byculla station using 110MT & launching of 40M span of public FOB girders at Sion station using 250T road crane.

The Block is to be operated as under:

Block 1:

Date of Block: 27/28.09.2025 (Saturday/Sunday night time)

Duration of Block: 00.30 hrs to 04.30 hrs of 28.09.2025

Traffic Block Section: o­n UP & DOWN Slow & Fast Lines between Byculla and Parel.

Block 2:

Date of Block: 27/28.09.2025 (Saturday/Sunday night time)

Duration of Block: 01.10 hrs to 04.10 hrs of 28.09.2025

Traffic Block Section: o­n UP & DOWN Slow Lines & Fast Lines between Dadar And Kurla

Repercussions o­n Suburban Trains :

Dadar – Kurla local leaving Dadar at 22.18hrs will remain