966 MWs for November, 1056 MWs from Dec-25 to Feb-26

Srinagar, Oct 7: With the onset of winters, Ministry of Power (MoP) has allocated over 870 Megawatts (MWs) of power for Jammu and Kashmir and Ladakh from the from unallocated quota of Central Generating Stations (CGSs) of northern region.

The official documents reveal that the MoP has ordered the concerned authorities to execute the share of 44 percent (877.42 MWs) un-allocated quota of CGS’s to Jammu and Kashmir and Ladakh with effect from October-01.

The MoP in the allocation percentage for winter months for the year 2025-26 has said that of the total un-allocated quota of CGSs of northern region, Jammu and Kashmir is receiving 44 percent for the month of October-2025, 49 percent for November-2025, 54 percent till December-2025 to F