Demolition of the south bridge for the Arlington Avenue Bridges Project is mostly complete, with crews now clearing debris and dewatering the site to prepare for excavation and construction of the new bridge.

Work on the north bridge continues, with crews preparing for the first concrete pour on the bridge deck next week, weather permitting.

Once cured, the north bridge will provide a critical access route for heavy equipment during the reconstruction of the south bridge.

Arlington Avenue Bridges Project Close +2 +2 +2

The project, managed by the Regional Transportation Commission of Washoe County, replaces two nearly century-old bridges over the Truckee River in Wingfield Park.

The project is designed to improve safety for pedestrians, bicyclists, transit users,