On Tuesday, the Tucson Unified School District (TUSD) Board went over the next project that will be covered by the TUSD Bond 2023.

Of the $480 million, $54 million have already been used on things like cyber security devices, HVAC systems, fields and more.

So whats next? The district's next focus targets health office upgrades across multiple campuses, according to Dr. Charlotte Carter, TUSD Bond Program Manager.

She said they just upgraded four and in summer 2026, the next five school's will receive a facelift to their health offices.

Those schools include Mission View Elementary, Pistor Middle, Rincon High, Safford K-8 and Santa Rita High.

The estimated price for the project at each school is $75,000, plus an additional $75,000 for contingency.

The $450,000 project will ensure the