STARBASE, Texas (ValleyCentral) —Wrapping up the rest of this week's update, LabPadre is seeing major changes happening at the launch complex.

Crews are preparing for the demolition of Pad 1's launch mount, the existing chopsticks are in for a major overhaul, Pad 2's launch mount construction is still underway, and Massey's outpost fueling infrastructure continues to be repaired.

Down at the launch complex, the push is on to demolish the outdated equipment at Pad 1.

On Sunday, crews got to work on the chopsticks, removing the pusher cars and ship lifting pins from the arms.

On Monday, demolition of the berm between Pad 1 and the tank farm began, with excavators breaking up and pulling down a section of the barrier's concrete cover.

On Tuesday and Wednesday, the vent lines were removed