KISHTWAR, Nov 1: Deputy Commissioner Kishtwar, Pankaj Kumar Sharma today chaired a comprehensive review meeting to assess the progress of road infrastructure projects being executed under the Pradhan Mantri Gram Sadak Yojana across all sub-divisions of the district.

During the meeting, the Executive Engineers (PMGSY) briefed the Deputy Commissioner on the current status, physical achievements and challenges encountered in the execution of various projects. A detailed PowerPoint presentation was also given outlining project-wise progress and timelines.

It was informed that in Division Kishtwar, out of 99 sanctioned projects, 58 have been completed, while work on 41 are in progress. In Marwah Division, 13 out of 21 schemes are complete and work on 5 others is underway.

The DC took a detai