PHOENIX — A $19 million project to resurface Interstate 10 in Tonopah near Salome Road has been completed.
The project started in March between mile markers 80 and 90 with construction crews also replacing guardrails, signage, fencing and making bridge repairs.
Arizona Department of Transportation said in a release that drainage was also added in the area.
Construction completed ahead of schedule
The project was expected to be done in 11 months, which would have led to a January completion date.
Workers performed most of the work overnight from 7 p.m. to 6 a.m. on weekdays in order to minimize traffic impacts and finish early.
The Federal Highway Administration assisted ADOT in the construction.