MP Indra Hang Subba chaired a review meeting with NHIDCL to ensure progress on Sikkim's highway projects, focusing on NH-10.
Frequent landslides and monsoon damages on NH-10 were identified as major challenges, disrupting traffic and infrastructure stability.
NHIDCL plans to reinforce five vulnerable sections of NH-10, with MP Subba urging completion within six months before the next monsoon.
In a bid to ensure uninterrupted connectivity and timely completion of highway works in Sikkim, Lok sabha MP Indra Hang Subba chaired a high-level review meeting with senior officials of the National Highways and Infrastructure Development Corporation Limited (NHIDCL) at its headquarters in New Delhi. The meeting focused on assessing the current status and progress of projects alo