PORTSMOUTH, Va. — Dominion Energy says its massive Coastal Virginia Offshore Wind (CVOW) project remains on schedule, despite final reviews revealing minor issues that have delayed the start of turbine installation.

The company confirmed that its turbine installation vessel, Charybdis, the first all-American offshore wind vessel of its kind, is undergoing final remediation work at the Portsmouth Marine Terminal.

During the final inspection, state regulators identified “punch list” items that need to be addressed before the vessel can begin turbine loadout and installation.

Dominion officials said the items involve quality assurance details, not major system issues.

“All major systems are operating well,” Dominion Energy said in a statement. “The vessel is expected to be cleared to lo