Indore (Madhya Pradesh): In the State’s commercial capital, a crucial power infrastructure project has come to a grinding halt over a land ownership dispute between the Indore Development Authority (IDA) and Madhya Pradesh Power Transmission Company (MP Transco).
The proposed 132 kV extra high tension (EHT) Substation at Retimandi Naka, envisioned as a key reinforcement to Indore’s expanding power network, remains on paper as officials from both agencies exchange conflicting claims over the land.
Dispute over possession and ownership
According to IDA chief executive officer Dr Parikshit Zade, the authority has already handed over possession of the land to MP Transco.
“The IDA has given possession of the land. It is now for MP Transco to approach the revenue department and get the land