Syracuse, N.Y. -- Micron Technology will delay opening its first two chipmaking factories in Clay by two to three years, the company said in a report made public today.
That would mean the first factory wouldn’t open until eight years after Micron announced in 2022 it planned to build in Central New York.
Micron said earlier this year that the first fabrication plant, or fab, was scheduled to open in mid-2028. The opening has now been moved back to late 2030.
Completion of the second fab has been pushed back from late 2030 to late 2033, the company said in the final environmental report on the project, released today.
The environmental report was formally accepted and made public today by the Onondaga County Industrial Development Agency. Acceptance of the report is a critical ste