The Athletics gave a rundown Thursday of what to expect as their Las Vegas ballpark progress moves into the new year and beyond.

Using an animated 3D computer model, the A’s showed the Las Vegas Stadium Authority a detailed presentation of how the stadium will begin to come together over time, as the project remains on track for its early 2028 completion date .

The majority of the work over the next several months will be concrete-related, with the pouring of the various stadium concourse decks. The first of those has already been poured, with the initial portions of the lower concourse coming into form.

Some steel work will begin in the spring, with installation of the steel that will support the roof of the structure to kick off in the summer, according to A’s chairman Sandy Dean.

Af