Mangaluru: Several major railway projects in Karnataka have come to a halt due to delays in land acquisition by the state government, even as the Centre has sharply increased funds for railway development in the state.
According to a report published by The New Indian Express on Friday, in a written reply to the Lok Sabha, Railway Minister Ashwini Vaishnaw said Karnataka needs 9,020 hectares of land for various railway projects, of which 63% (5,679 ha) has been acquired, while 3,341 ha is still pending.
Dharwad–Belagavi via Kittur new line (73 km), taken up under a 50:50 cost-sharing agreement with the state. The project has made no progress reportedly, because the required land has not been handed over. As per the agreement, land is to be provided free of cost by the state.
The other p