Here are the latest updates on five transportation projects happening in the Conroe area.

Ongoing projects

Hwy. 75 improvements

Project: Hwy. 75 between South Loop 336 North and Gladstell Street is undergoing improvements such as planing and base repair.

Update: According to a July 8 media update from the Texas Department of Transportation , this project is 20% complete.

Timeline: first quarter of 2025-fourth quarter of 2025

Cost: $3.3 million

Funding source: state funds

Hwy. 105 widening

Project: Hwy. 105 is being reconstructed and widened from two to four lanes between 10th Street and South Loop 336.

Update: This project is 42% complete, according to TxDOT.

Timeline: March 2023-second quarter of 2028

Cost: $52.65 million

Funding source: state funds