Here are the latest updates on five transportation projects happening in the Conroe area.
Ongoing projects
Hwy. 75 improvements
Project: Hwy. 75 between South Loop 336 North and Gladstell Street is undergoing improvements such as planing and base repair.
Update: According to a July 8 media update from the Texas Department of Transportation , this project is 20% complete.
Timeline: first quarter of 2025-fourth quarter of 2025
Cost: $3.3 million
Funding source: state funds
Hwy. 105 widening
Project: Hwy. 105 is being reconstructed and widened from two to four lanes between 10th Street and South Loop 336.
Update: This project is 42% complete, according to TxDOT.
Timeline: March 2023-second quarter of 2028
Cost: $52.65 million
Funding source: state funds
I-45 high-occ