BREITUNG TOWNSHIP — Work is expected to begin next month on an almost $400,000 project to realign and repave E Bar D Road off Lake Antoine Road.

Bacco Construction of Iron Mountain will be the contractor after submitting the low bid of $381,710.30. They likely will start in mid-September, with the goal of having it completed by Nov. 1, said James Harris, Dickinson County Road Commission managing director.

The project will crush, shape and pave about 3,000 feet of E Bar D Road from where it meets Lake Antoine Road to where the paved portion now ends.

The junction also will be shifted and a hill cut done to reduce the grade and square it with