The Venice Municipal Fishing Pier is undergoing $410,000 in repairs following hurricane damage.
Hurricanes Helene and Milton damaged the pier's T-section framing, decking, and railing last summer.
Repairs are expected to be completed by the end of September.
The pier's main structural components remain intact and are not being replaced.
The undamaged portion of the pier and bait shop remain open to the public during construction.
VENICE – Repairs of hurricane damage to the Venice Municipal Fishing Pier continue, with contractor Tampa Bay Marine Inc. hoping to have the project complete by the end of September.
The scope of the $410,000 project includes removal and replacement of hurricane--damaged framing, decking and railing on the pier's T-section, leaving pri