ASHLAND, Kentucky (WSAZ) - Beginning Sunday, September 7th contractors will be inspecting the structural components of the 12th Street (green) and 13th Street (blue) bridges.

According to a release from Kentucky Transportation Cabinet, contractors will be using climbing gear, lifts, and specialized trucks to inspect the bridges that carry drivers that use US 23 and US 60 through Kentucky and Ohio.

This inspection will require a full closure of the 12th Street Bridge from Sunday, September 7 through Saturday, September 13.

Beginning on Monday, September 15, drivers who take the 13th Street Bridge will be impacted by single lane closures that go through Friday, September 19.

Any road work schedules could be subject to change depending on weather conditions.

Drivers are being asked to