Indian Prairie School District 204 is beginning the first full year since the approval last fall of a $420 million bond referendum , and officials describe it as an exciting time with much transformation ahead.

Upcoming projects to be funded through the Safer, Stronger 204 program were the topic of a building operations presentation this week to the school board. Here are the highlights of what’s ahead.

Major renovations at Neuqua Valley

The architect and construction manager are in place for a $96 million modernization of Neuqua Valley High School by the start of the 2028-29 school year. The work will provide space to bring back freshmen for the first time since 2003 and add classrooms, science labs and collaborative work spaces.

Chicago-based Bulley & Andrews is the project’s cons