The Australian Rail Track Corporation (ARTC) will carry out essential maintenance and improvement works across the Hunter Valley network this week.

As a result, the shutdown is scheduled to impact:

From Kooragang to Turrawan and Muswellbrook to Ulan from 6.30am on Tuesday 23 September to 6.30am on Friday 26 September

Waratah to Telarah from 8.30pm on Tuesday 23 September to 3.30am on Thursday 25 September

Crews are focusing on critical upkeep and defect removal, including track geometry repairs, track component replacements, and other scheduled programs.

Additional activities include 400m track reconditioning, approximately 5km of rerailing, culvert installations, bridge repairs and turnout renewal.

“The Hunter Valley rail network requires ongoing maintenance to maintain its vital ro