Fransen Pittman Construction was awarded the contract for a Grapevine water and wastewater plant building improvements project.
The Colorado-based company with a Southlake location was awarded a guaranteed maximum price contract for $20.75 million for the construction at the Sept. 16 meeting .
The details
The project includes two new administration buildings, one located at the water treatment plant and another at the wastewater treatment plant. The proposed project also includes new maintenance facilities at both sites. Construction is scheduled to start in October and is expected to be completed within 18 months, according to city documents. Grapevine council approved the bonds for the work in April 2024, according to previous reporting .
The wastewater building is at 602 Shad