There are five transportation projects that are either slated to begin in 2026 or are already underway in Flower Mound and Highland Village.

Upcoming projects

1. FM 2499 and FM 3040 intersection improvements

Project: Reconfiguration to provide a dual left turn, three thru lanes, and a dedicated right turn lane for each direction, while maintaining the dual right turn lanes for eastbound traffic.

Update: Flower Mound Town Council approved an interlocal agreement to obtain funding from Denton County for the project. Council members are expected to approve a further $500,000 to the projected $3 million project cost through a Capital Improvement Plan amendment, officials said.

Cost: $3.5 million

Funding sources: Denton County funds, impact fees and town capital project funds

Timelin