After a spirited debate Monday, Chatham-Kent councillors approved the construction tender for the new Chatham-Kent community hub.
After a spirited debate Monday, Chatham-Kent councillors approved the construction tender for the new Chatham-Kent community hub.
The approximately $39.3 million contract was awarded to Fortis Construction Group Inc. of Tecumseh, coming in $3.6 million under the estimated construction cost.
Recommended Videos
With this approval, the project will move forward into the construction phase. Work is expected to begin in December, with completion anticipated in early 2028.
The hub will bring together a new civic centre, library and museum at the former Sears location in the Downtown Chatham Centre.
Overall, the project budget is $52.8 million, including about $7