According to MRVC, during the coordinated night operation, saw the launching of four girders for the MIDC Road Overbridge (ROB), five girders for the Ambernath (Kalyan-end) Foot Overbridge (FOB), and the dismantling of the Badlapur FOB as well as both spans of the Ambernath (Karjat-end) FOB

The Mumbai Railway Vikas Corporation (MRVC) successfully completed several key infrastructure works in the Kalyan–Badlapur section during a 90-minute night block between 2.15 am and 3.45 am on Saturday.

According to MRVC, during the coordinated night operation, saw the launching of four girders for the MIDC Road Overbridge (ROB), five girders for the Ambernath (Kalyan-end) Foot Overbridge (FOB), and the dismantling of the Badlapur FOB as well as both spans of the Ambernath (Karjat-end) FOB. Read More