GROVE CITY, Pa. - The Grove City Area School District Board of Directors approved final contracts for renovations to Forker Field Stadium at Grove City High School.
The contract was approved at the Board's meeting held on Monday, November 10. The $1.37 million renovation project will be funded through the district's Capital Reserve Funds and will not require any new borrowing or use of general operating funds.
Renovations will include a new press box, canopy and risers, as well as an upgraded audio system and new lighting and electrical work.
The construction and permitting process is expected to begin this winter, and the project is expected to be fully completed before graduation in June of 2026.
This project represents the third major upgrade for the stadium within the past five ye