ANNAPOLIS, Md. — Maryland officials have more than doubled the estimated cost to replace Baltimore's Francis Scott Key Bridge, which collapsed and killed six construction workers last year after a massive container ship crashed into it, and they've added two years on to the projected completion date.

What You Need To Know

Maryland officials have more than doubled the estimated cost to replace Baltimore’s Francis Scott Key Bridge, which collapsed and killed six construction workers last year after a massive container ship crashed into it

Maryland officials are also adding on two years to the projected completion date

The Maryland Transportation Authority says it is updating its financial forecast to include a price range of between $4.3 billion and $5.2 billion dollars, with an anticipa