Nanded: The government has launched the second phase of the Prime Minister Awas Yojana (PMAY), under which the zilla parishad has been assigned a target of constructing 2,40,404 houses. However, only 4,782 have been completed so far. Implementation has been hampered by issues such as a lack of land, Aadhaar updates, transfers, bank guarantees and other obstacles. As a result, 2,35,622 houses remain pending, leaving the ZP struggling to meet the scheme’s target.
This year’s PMAY target of 2,40,404 houses is being implemented through the district rural development agency. Applications were invited across 16 talukas. Based on geotagging and other criteria, 2,24,519 applications were sanctioned, while the remaining 15,885 are still pending. Only 4,782 applicants received all four instalments