The Central Railway will impose a series of night-long traffic and power blocks across the Panvel–Kalamboli and Nilje–Dativali sections between November 21 and December 8 to carry out infrastructure works. The blocks will result in the regulation, diversion, and rescheduling of several long-distance trains on specific nights, starting Friday.
The work includes the removal or rectification of infringements that come close to the railway safety zone with regard to the Panvel–Kalamboli Coaching Complex and the dismantling of the Sheel Phata Road Overbridge for the dedicated Freight Corridor project, the Central Railway said in a statement on Thursday.
The block between Panvel and Kalamboli has been enforced from November 20 midnight to December 2. Railway officers said the work linked to th