ROCK SPRINGS — The results of a structural analysis into the Rock Springs Civic Center revealed a price tag of $15.6 million over the next 20 years to repair the building.
FEA, the company contracted to review the center, recommends $15.6 million for the building from 2026 to 2045. $7.5 million accounts for major maintenance including plumbing, electrical repairs, roofing, and HVAC work. $5.6 million is recommended to be spent on the building during 2026 and 2027 for repairs and potential Americans with Disabilities Act improvements. $2.5 million is being recommended for preventive and corrective maintenance. The report recommends additional major maintenance work to take place during the 2040s and 2050s.
“There are some other major maintenance system-type replacements that will need to

Sweetwater Now