Sets timelines for Issue Resolution, completion of work

RAJOURI, DECEMBER 12: District Development Commissioner Rajouri, Abhishek Sharma today reviewed the progress of widening and upgradation works on National Highway 144 from Sunderbani to BG sector stretch. The review meeting focused on accelerating the pace of work and removing bottlenecks to ensure timely completion of the road project.

The DDC took a detailed assessment of the Thandapani, Bakhar and Galuthi Kotli stretches. Discussions were held regarding land-related disputes, requirement for additional land acquisition, identification of dumping locations and estimated timeline for completion of each section.

Stressing the need for uninterrupted execution, the District Development Commissioner directed the concerned agencies to