The Indiana Department of Environmental Management halted some construction work at the $11 billion Amazon data center under construction by New Carlisle, so it does not further infringe upon wetlands.

IDEM cited the e-commerce giant and its general contractor Walbridge Construction for impacting marshes on the property.

"Amazon was sent a non-compliance letter. As noted in the letter, the company self-reported the incident and was cited for impacting wetlands without authorization," IDEM Communications Director Allen Carter said.

The regulatory agency is asking them to resubmit their plans for the wetlands on the site in St. Joseph County, not far from the LaPorte County border. Amazon withdrew its original wetlands permit application after the construction work infringed on the marshe