KEY TAKEAWAYS:
Regulators to vote early on Entergy ‘s power plant for Meta ‘s planned data center
Some advocacy groups oppose fast-tracked decision, citing secrecy and fairness
Project promises 6,500 construction jobs and 500 permanent Meta jobs
Meta commits to 1,500 MW of solar generation with Entergy
Fast-tracking a vote that was originally expected to happen two months from now, state utility regulators plan to decide tomorrow whether to approve a controversial power plant Entergy wants to build specifically for tech company Meta to run a giant data center planned for Northeast Louisiana.
A utility ratepayer advocacy group that opposes the project says this attempt to rush the Louisiana Public Service Commission ‘s approval has been shrouded in secrecy and “back door deal

N.O. CityBusiness