LEWISBURG — Supervisors in East Buffalo Township will rebid the construction contract for the new bridge over Turtle Creek.

At a special meeting Wednesday, the township supervisors rejected the bids for the construction of an 8-foot reinforced concrete bridge deck and associated parapet. The damaged bridge on Turtle Creek Road shifted off its foundation during a severe storm in August 2023.

A fifth beam is needed to accommodate tractor-trailer traffic under PennDOT requirements.

"An extra beam had to be added because of the very short depth of the beams," construction engineer Jason Snyder, of ETA Inc., said. "We came to an agreement that a fifth beam had to be added to the bridge. I didn't open the bridge because we felt we didn't give them enough time to address the change to the supe