South Broadway will experience lane closures near Denver starting Sunday evening as the City of Littleton works to both replace a culvert and construct a pedestrian walkway. "Significant" traffic impacts are expected through spring 2026, and the broader project is expected to be complete by fall of 2026.

City officials said they can accomplish two things at once, as replacing the culvert will require crews to dig a 30-foot trench into Broadway. That will allow them the opportunity to add a pedestrian underpass in the area of Broadway and Dry Creek Road.

"It's a big project. It is a project that normally is something that's a 5- to 10-year scale, and the fact that we're under construction in less than a year with the funding in place is (a) tremendous effort," Littleton Water Resources En