SIOUX FALLS, S.D. (KELO) -- With Sioux Falls wrapping up its construction season for 2025, the city of Sioux Falls examines what's next for several of the city's construction projects that will stretch into 2026.

Typically, the average construction season in Sioux Falls runs from March through November, depending on the weather.

Arrowhead Parkway & Veterans Parkway intersection

The Veterans and Arrowhead parkway intersection is a major reconstruction project that, when completed, would make the intersection the largest in the state.

Some additions they plan on making to the intersection are lowering the intersection 3–5 feet, adding three pedestrian tunnels, relocating detention ponds, adding dual left-turn lanes from all directions, and realigning the roadway to improve horizontal and