Read about some of the latest updates on transportation projects in the Katy-Fulshear area. This list is not comprehensive.
Upcoming projects
Second Street parking lot
Project: The project will replace the current asphalt and gravel lot with concrete, bringing 68-78 spots to the northwest corner of Second Street and Avenue A near downtown. The project will also add new sidewalks and concrete driveways.
Update: At an Oct. 13 meeting, Katy City Council unanimously approved a construction contract with Castillo-Aranda LLC.
Timeline: December-April 2026
Cost: $651,725
Funding source: city of Katy
Municipal Court parking lot
Project: The project will expand the lot by 42 spaces as well as add security measures, storm drainage and sidewalk extensions.
Update: At an Oct. 13 meet