From road reconstruction to pavement joint sealing, check out the latest on five transportation projects across Flower Mound.
Upcoming projects
Amhearst Lane
Project: Work will include fully reconstructing the street, sidewalk and barrier-free ramps on the roadway, and rebuilding the water main and portions of the sewer line under the road.
Update: A design contract for the road’s improvements was approved by council at the Nov. 17 meeting.
Timeline: no timeline provided
Cost: $2.7 million
Funding sources: Flower Mound street reconstruction bonds and utility debt
Lakeside Parkway
Project: Construction will include the replacement of deteriorating concrete panels along Lakeside Parkway between Long Prairie Road and the town limits.
Update: Flower Mound Town Council approved