Nueces County is seeking a new contractor to build the restaurant at Bob Hall Pier.
The pier itself is on schedule for completion by late 2025 or early 2026, but the restaurant will be delayed.
The project has faced cost increases, requiring additional funding and a deductive change order.
Nueces County commissioners are looking for another company to build the restaurant at Bob Hall Pier.
While the new $28.5 million pier is on schedule to be completed by the end of 2025 or early 2026, the pier contractor, Callan Marine, will not build the new restaurant and concession area, and the restaurant that was proposed to open in mid-2026 will be completed at a later date.
During a walking tour of the pier on North Padre Island on Aug. 12, guests explored the pier and fut