A legal challenge by Walsall Council to block a controversial green belt development in Great Barr has been dismissed by the courts.
Deputy leader of Walsall Council, Councillor Adrian Andrew, said the court’s decision to allow the 3.2 hectare Battery Energy Storage System (BESS) off Chapel Lane was ‘disgraceful’.
READ MORE: The £4.7m cost of cracking down on yobs and flytipper s
Now, developer Anesco has permission to go ahead with its plans to develop the facility which will have 44 storage units, two substations, and a 15-metre communications tower.
The authority has long-opposed the development for reasons including fire safety risks, loss of green belt land, noise and industrial appearance.
The intended lifespan of the ‘temporary’ facility is 40 years, with its p