GENESEE COUNTY, MI – Repair work is scheduled to begin next week on the I-75 bridge at Fenton Road.

Beginning Monday, Aug. 11, work on the bridge will include concrete substructure patching, resealing bridge joints, steel rocker bearing realignment, steel beam repairs, heat straightening, painting and temporary supports.

Daytime left lane closures with traffic shifts will be implemented from 8 a.m. through 2 p.m. as needed on both directions of I-75 at Fenton Road, according to a Michigan Department of Transportation news release. One lane of traffic remain open in each direction.

Daytime right lane closures will be used as needed from 7 a.m. through 3 p.m. on southbound Fenton Road.

The work is estimated to be completed by Aug. 28 and is part of a $2.7 million investment to improve