Here are five transportation updates from across the Lake Travis-Westlake area for December, according to Bee Cave, Lakeway and Texas Department of Transportation officials.

Ongoing projects

Hwy. 71 Safety Improvement Project

Project: implementing medians on Hwy. 71 from Bee Creek Road to Bee Cave Parkway

Update: finalizing construction of the medians and closing out the project

Timeline: completion expected early 2026

Cost: $2.8 million

Funding source: federal funding

Loop 360 Courtyard Drive/RM 2222

Project: removing traffic signals from mainlanes and constructing an underpass at Courtyard Drive; reconfiguring RM 2222 to include a diverging diamond interchange; addition of shared-use paths and sidewalks

Update: excavation is ongoing of the west cliffs adjacent to southbo