Just in time for the busy travel season, Amtrak has announced it has completed the reconstruction of the North Platform at Lancaster Station.

The North Platform returned to service earlier this month after being closed for 10 months of construction.

Project highlights include:

North Platform:

Demolition of the existing platform and foundations

Construction of new foundations and platform panels

Rehabilitation of the canopy structure and baggage building

Restoration of exterior and interior stairwells

New overhead catenary system installed

South Platform

Reconstructed and returned to service in Nov. 2024

Pedestrian Overpass

New roof installation

Carpet removal and terrazzo flooring repair

Window replacements

Insulation added

Station Building:

Window and main entrance door